1.         Explain the concept of aggregate
planning.  How do we disaggregate the
aggregate        plan?
2.         a.         What are the basic attributes of
Quality?      
            b.         How
can Control Charts help in controlling the delivery time of home delivery of                          Pizzas?
3.         a.         How can we enhance productivity in
Indian Manufacturing and retail sectors?
            b.         Explain
the concepts of work sampling and time study.
4.         a.
        Explain the Cycle View   of   Supply
  Chain   Management. 
What   are   the  major
                        decisions
to be taken for an effective SCM?
            b.         Bob
Fero is   an   operations   analyst for Sell-Rite Discount stores of
Washington,                                     D.C. He is currently studying the   ordering   and   stocking
  policies  at Sell-Rite’s                                    central
warehouse for one of its best-moving items, a child’s toy. An examination                        of historical supply and
demand data for this item indicated and almost constant                              lead time (LT) of  10 days,  and   abundant
  production   capacity    allowed  very                              consistent
production  and  delivery times. Bob also discovered that the
demand                                   per
day(d) was nearly normally distributed with a mean (d) of 1,250 toys per day                             with a standard
deviation (σd) of 375
toys per day. 
                        i)
         Compute the order point for the
toy if the service level is specified at 90%                                    during lead time. 
                        ii)         How much safety stock is provided in
your answer in Part A?
Section-B
Case
study
A company receives parts from suppliers
to be used in its manufacturing departments. The quality control department
must perform two operations when shipments and received: Operation A—draw a
random sample, package, and deliver to testing, and Operation B—test the
materials and issue a disposition report. The time estimates for processing six
shipments through quality control are:
| 
Shipment | 
Operation A (hours) | 
Operation B (hours) | 
| 
1 | 
1.3 | 
0.9 | 
| 
2 | 
1.3 | 
1.1 | 
| 
3 | 
0.8 | 
1.5 | 
| 
4 | 
1.6 | 
1.4 | 
| 
5 | 
1.5 | 
1.0 | 
| 
6 | 
1.2 | 
1.9 | 
5.         Case Questions:                                                                     
a.                 
Use Johnson’s rule to set the sequence of
processing the shipments through quality control. (Operations need change over
to new jobs at the same time.)
b.                 
How much total time is required to process the
six shipments through quality control? What is the idle time on each operation
A & B?
 