1. The Following is a sample
data set.
10 8 8 6 5
What is the variance of this
data set?
a. 3.0
b. 3.8
c. 7.3
d. 7.4
2. An auditor should use a
histogram in a quality audit to do which of the following?
a. Provide objective evidence
that the audited uses statistical process control (SPC)
b. Expose patterns that are
normally difficult to detect
c. Interpret data for a trend
chart
d. create a stratified tally
diagram
3. Comparing how a process is
actually performed against the documented work instruction for that
process is an example of
which of the following techniques?
a. Quantitative
b. Qualitative
c. Statistical
d. Random sampling
4. Attribute sampling should
be used when
a. The data are measurements
in metric units.
b. Ayes-or-no decision is to
be made.
c. The population has
variability.
d. A multi-stage sampling
plan is needed.
5. Scatter diagrams are best
described as
a. Histograms.
b. Correlation analysis.
c. Pareto analysis.
d. Ishikawa diagrams.
6. If data are plotted over
time, the resulting chart will be a
a. Run chart
Examination Paper of Six Sigma Green Belt
IIBM Institute of Business Management 2
b. Histogram
c. Pareto chart
d. Poisson distribution
7. To determine who are or
might be customers for a specific process, it would be most useful to create a
a. Pareto chart
b. Flow diagram
c. Cause and effect diagram
d. Scatter diagram
8. A production line uses
signs at specific points on the line to indicate when components or raw
materials
need to be replenished. The
practice is an example of
a. Kanban
b. Poka-yake
c. Checkpoints
d. Hoshin
9. Which of the following is
a good tool for planning cycle time reduction and concurrent operations?
a. A timeline
b. A Pareto diagram
c. An X and R chart
d. A PERT chart
10. Attribute and variable
data are best described as which of the following? Attribute variable
a. Counted values measured
values
b. Counted values visual
features
c. Measured values counted
values
d. Visual features counted
values
11. All of the following are
common ways for people to react to conflict EXCEPT
a. Competing
b. Collaborating
c. Avoiding
d. Sabotaging
12. A quality manager has
chosen to survey customer satisfaction by talking samples based on the
categories of frequency of
use, categories of use, and demographic. This technique is known as
a. Random sampling
b. Data collection
c. Stratification
d. Customer classification
13. Which of the following
actions is Not used to reduce process cycle time?
a. Analyzing current
processes
b. Reducing queue times
c. Setting priorities
d. Implementing
activity-based costing
14. A company’s accounts
payable department is trying to reduce the time between receipt and payment
of invoices and has recently
completed a flowchart. Which of the following tools would be the for them to
use next?
Examination Paper of Six Sigma Green Belt
IIBM Institute of Business Management 3
a. Fishbone diagram
b. Scatter diagram
c. Box and whisker plat
d. Histogram
15. In a manufacturing
company, the machine shop is what kind of customer in relation to the human
resource department?
a. Intermediate
b. Hidden
c. External
d. Internal
16. The primary purpose of a
project charter is to
a. Subdivide the project into
smaller, more manageable components
b. Provide management with a
tool for selecting a project that addresses business needs
c. Provide management with a
tool to ensure that project deadlines are met
d. Provide the project
manager with authority to apply organizational resources to project activities
17. Sample selection of parts
for inspection must be selected at random to ensure
a. A minimum sample size.
b. The probability of not
rejecting the lot
c. The probability of
accepting the lot
d. Finding typical
characteristics of the lot.
18. Which of the following
are bases for establishing calibration intervals?
I. Stability
II.Purpose
III.Degree of usage
a. I and II only
b. I and III only
c. II and III only
d. I, II, and III
19. Specification limits are
derived from which of the following?
a. Process capability studies
b. Process control charts
c. Customer requirements
d. Historical data
20. The primary purpose of a
control chart is to
a. Set Specifications and
tolerances
b. compare operations.
c. Determine the stability of
a process.
d. Accept or reject a lot of
material
21. When a control chart is
used on a new process, capability can be assessed at which of the following
times?
a. Before the chart is first
started
b. After the first ten points
are plotted
c. When the plotted points
hug the centerline
d. After the process is shown
to be in control
Examination Paper of Six Sigma Green Belt
IIBM Institute of Business Management 4
22. Precision is best
described as
a. A comparison to a known
standard
b. The achievement of
expected outgoing quality
c. The repeated consistency
of results
d. The difference between an
average measurement and the actual value
23. The overall ability of
two or more operators to obtain Consistent results repeatedly when measuring
the same set of parts and
using the same measuring equipment is the definition of
a. Repeatability
b. Precision
c. Reproducibility
d. Accuracy
24. Which of the following
conditions must be met for a process to be in a state of statistical control?
a. Most of the product out by
the process is in specification.
b. All subgroup averages and
rang are within control limits.
c. All variation has been completely
removed
d. Previously optimal process
settings are used.
25. Which of the following
measures of dispersion is equal to the sum of deviations from the mean
squared divided by the sample
size?
a. Range
b. Standard deviation
c. Variance
d. Mode
26. An X and R chart is used
to
a. Indicate process variation
b. Specify design Limits
c. Interpret costs
d. Identify customer
expectations
27. Which of the following is
the most useful graphical tool for promoting an understanding of process
capability?
a. A flowchart
b. a histogram
c. An affinity diagram
d. An Ishikawa diagram
28. The type of chart that
presents the value of items in descending order is a
a. Histogram
b. Pareto chart
c. U chart
d. Cusum chart
29. Measures of which of the
following provide attributes data?
a. Temperature in degrees
b. Attendance at meetings
c. Weight in pounds
d. Length in metric units
Examination Paper of Six Sigma Green Belt
IIBM Institute of Business Management 5
30. The fraction of
nonconforming products is plotted on which of the following types of control
chart?
a. P chart
b. U chart
c. Np chart
d. C chart
31. A cause and effect
diagram is a useful tool for doing which of the following?
a. Determining the flow of a
process
b. Detecting shifts in a
process
c. Developing theories based
on symptoms
d. Arranging theories by
defect count
32. Which of the following
statistics would best describe the central tendency of a sample of data?
a. Mode
b. Mean
c. Standard deviation
d. Range
33. Which of the following
types of tools or techniques is considered qualitative?
a. Histogram
b. Frequency distributions
c. Pareto chart
d. Process observations
34. Which of the following
techniques is most useful in narrowing issues and limiting discussion?
a. Brainstorming
b. Quality function deployment
c. Cause and effect analysis
d. Mutilating
35. In statistics, an
estimation error that is persistent or systematic is called
a. Bias
b. Sensitivity
c. Random
d. Shift
36. A customer satisfaction
survey used the following rating scale:
1= very satisfied
2= Satisfied
3= Neutral
4= dissatisfied
5= very dissatisfied
This is an example of which
of the following measurement scales?
a. Nominal
b. Ordinal
c. Ratio
d. Interval
37. Which of the following
techniques is used in identifying underlying problems?
a. Cause and effect analysis
Examination Paper of Six Sigma Green Belt
IIBM Institute of Business Management 6
b. Prioritization matrix
c. Force field analysis
d. Pareto analysis
38. For a normal
distribution, two standard deviation on each side of the mean would include
what
percentage of the total
population
a. 47%
b. 68%
c. 95%
d. 99%
39. In measurement system
analysis, which of the following pairs of data measures is used to determine
total variance?
a. Process variance and
reproducibility
b. Noise system and
repeatability
c. Measurement variance and
process variance
d. System variance and bias
40. Process data being used
in the initial set-up of a process are assumed have a normal distribution. If
the
nominal (target) is at the
center of the distribution, and the specification limits are set at = 3 from
the
center the Cpk is equal to
a. -0.25
b. 1.00
c. 1.33
d. 1.67
41. A green belt is going to
monitor the number of defects on different size samples. Which of the
following control chart would
be most appropriate?
a. u
b. np
c. c
d. p
42. Correction,
over-production, inventory, and motion are all examples of
a. waste
b. 5S target areas
c. Noise
d. Value-added activities
43. The primary factor in the
successful implementation of six sigma is to have
a. The necessary resources
b. The support/leadership of
top management
c. Explicit customer
requirements
d. A comprehensive training
program
44. Which of the following
types of variation is LEAST likely to occur in sequential repetitions of a
process over a short period
of time?
a. Cyclical
b. Positional
c. Temporal
d. Seasonal
Examination Paper of Six Sigma Green Belt
IIBM Institute of Business Management 7
45. The primary reason that
most companies implement six sigma is to
a. Reduce defects
b. Improve Processes
c. Improve profit
d. Increase customer
satisfaction
46. The term used to describe
the risk of a type I error in a test of hypotheses is
a. Power
b. Confidence level
c. Level of significance
d. Beta risk
47. One characteristic of
attributes data is that it is always
a. continuous
b. Discrete
c. Expensive to collect
d. Read from a scale of
measurement
48. Which of the following
tests may be used to determine whether a sample comes from a population
with an exponential
distribution?
a. T
b. F
c. Chi-square
d. ANOVA
49. Which of the following
tools are appropriate for a quality engineer to use in qualifying a process
that
has variable data?
I. An and R control chat
II. A his to gram
III. A cc hart
IV. A p chart
a. I and II only
b. II and III only
c. III and IV only
d. I, II, and IV only
50. The correlation
coefficient for the length and weight of units made by a process is determined
to be
0.27. if the process were
adjusted to reduce the weight of each unit by 0.5 ounce, the correlation
coefficient of the length and
weight of the units made by the new process would be equal to
a. 0.50
b. 0.27
c. 0.23
d. -0.23
51. A form, in either diagram
or table format, that is prepared in advance for recording data is known as a
a. Cause-and-effect diagram
b. Pareto chart
c. Flowchart
d. Check sheet
Examination Paper of Six Sigma Green Belt
IIBM Institute of Business Management 8
52. A major drawback of using
histogram in process control is that they
a. do not readily account for
the factor of time
b. Are relatively difficult
to construct and interpret
c. Require too many data
points
d. Require too many intervals
53. Which of the following
tools would be of the greatest use for finding the most efficient path and
realistic schedule for the
completion of a project?
a. Interrelationship diagram
b. Activity network diagram
c. Tree diagram
d. Affinity diagram
54. A control plan is
designed to do which of the following?
a. Supplement information
contained in operator instructions
b. Support the production
scheduling system
c. Provide a documented
system for controlling processes
d. Provide a method for
tracking the design review process
55. To determine the average
number of nonconforming parts over time, which of the following attribute
control chart would be most
appropriate?
a. A chat
b. Np chart
c. P chart
d. U chat
56. Which of the following
techniques is most appropriate for generating continuous improvement ideas?
a. Tree diagram
b. Brainstorming
c. Prioritization matrix
d. Interrelationship diagraph
57. Which of the following
tools is used extensively quality function deployment (QFD)?
a. Affinity diagram
b. Matrix diagram
c. Cause and effect diagram
d. Activity network diagram
58. Which of the following
tools is most likely to be organizing a list of ideas generated during a
brainstorming session?
a. Activity network diagram
b. Affinity diagram
c. Histogram
d. Process control chart
59. Which of the following
tools would be most appropriate for collecting data to study the symptoms of
a problem?
a. A check sheet
b. A flow diagram
c. A force field analysis
d. An activity network
diagram
Examination Paper of Six Sigma Green Belt
IIBM Institute of Business Management 9
60. Kaizen is defined as
a. Re-engineering
b. Lean manufacturing
c. Continuous improvement
d. Error –proofing
61. The LEAST informative of
the four measurement scales is the
a. Ratio
b. Nominal
c. Ordinal
d. Interval
62. Which of the following
can used to determine the goodness of fit of a distribution to a data set?
a. T test
b. ANOVA
c. F rest
d. Chi square test
63. A fair coin is tossed 10
times. What are the expected mean and variance of the number of heads?
Mean variance
a. 0.5 0.025
b. 5.0 2.500
c. 5.0 5.000
d. 10.0 5.000
64. A process capability
analysis is NOT used to
a. Determine the ability of a
process to meet specifications
b. Maintain a process in a
state of statistical control
c. Establish new
specifications
d. Prioritize competing
processes
65. A type of line graph used
to assess the stability of a process is called a
a. Control chart
b. Pareto chart
c. Check sheet
d. cause and effect diagram
66. A process produces
nonconformities according to a distribution. If the mean of the nonconformities
is
25, what is the standard
deviation?
a. 2.5
b. 5.0
c. 12.5
d. 25.0
67. Five six-sided dice are