assignmentssolution@gmail.com

Get Assignments and Projects prepared by experts at a very nominal fee.

More than 8 years in assisting assignments and projects/dissertation/thesis of MBA,BBA,BCA,MCA,PhD and others-

Contact us at : Email : assignmentssolution@gmail.com

Help for : SMU, IIBM,IMT, NMIMS, NIBM ,KSBM, KAIZAN, ISBM, SYMBIOSIS, NIMS, IGNOU, XAVIER, XIBMS, ISM, PSBM, NSBM, NIRM, ISBM, ISMRC, ICMIND, UPES and many others.

Help in : Assignments, projects, M.Phil,Ph.D disseration & thesis,case studies

Courses,MBA,BBA,PhD,MPhil,EMBA,MIB,DMS,MMS,BMS,GDS etc

Contact us at : Email : assignmentssolution@gmail.com



Saturday, 9 April 2016

IIBM Exam papers/case studies:Contact us for answers at assignmentssolution@gmail.com

Examination Paper: Construction Management
1 IIBM Institute of Business Management

IIBM Institute of Business Management
Examination Paper MM.100
Construction Technology

1. Excavation carried out for construction of individual foundation and trenches is- :
a. Sloped excavation
b. Bulk excavation
c. Confined excavation
d. Excavation in rocks

2. Which of the following is not the temporary exclusion of controlling ground water?
a. Sump pumping
b. Cofferdams
c. caissons
d. Well point system

3. Strength, water-tightness, abrasion resistance are the properties of-:
a. Plastic concrete
b. Hardened concrete
c. Both a & b
d. None of these

4. The welding which is not suited for fabrication work known as-
a. Fusion welding
b. Friction welding
c. Flame welding
d. Metal arc welding

5. The most common heat sources used in industrial welding works are-
a. Electric welding
b. Resistance heating at an interface
c. Flame welding
d. All of the above


…………………………
9. RCC stands for _______________________________.

10. WMM stands for __________________________________.

Part Two:
1. What are the causes of accident at construction sites?

2. List the document required for actual project implementation.

3. What are the activities involved in plastering?

4. List the guidelines for storage of civil engineering construction material.


Caselet 1
The president rise in commodity prices across the board, s posing major threat to those working on construction projects, in general and real estate projects, in particular. The prices of raw material are it cement, steel, aluminum, plastics, etc., are seeing an upward rally. This can hamper the growth of the sector adversely in case the demand for these projects, worth crores of rupees, falls. The impact of this fall would be severe on country’s infrastructure development as well as the growth of the manufacturing sector. This lurking risk is not restricted only to domestic sector but is gaining global attention. Globally too project managers are concerned as commodity prices shoot through the roof. In addition to the problem of cost overrun, KPMG’s Global Construction Survey conducted in the year 2007 unraveled three major aspects of the construction sector; Current business trends, management of building process and the future. The findings revealed that the shortage of qualified contractors to bid for and execute ………………….
intervention by IT sector can also help the construction sector in reducing the man-managed deficiencies that contribute to cost and time overruns, if not eliminating it in entirely.
Questions:
1. The cost-effective construction technologies would emerge as the most acceptable case of sustainable technologies in India. Comment

2. Explain what lessons are required to be learned from International experiences and its own past experiences in construction project.

Caselet 2
The Euro Tunnel formerly known as Channel Tunnel project was conceived for over two centuries. However, it was in April 2, 1985, a formal invitation to complete the fixed link of it was floated by the British and the French. Thereafter, in January, 1986, the train/shuttle tunnel developed by the consortium channel Tunnel Group Limited-France-Manche S.A. (CTGFM) was ultimately given the contract. In the development of it, design engineering was the prime challenge. The challenge was overcome through construction of three concrete lined parallel tunnels of approximately 50 kilometers long running mostly

…………………………..water pressure were used. Lining of the tunnels were done with pre-cast concrete segmented rings and ductile iron as per soil conditions so as to ensure a 120 year life. The concrete used in the tunnel construction are of high strength and density so as to give optimum corrosion protection to the steel reinforcement. Besides, secondary protection against corrosion was ensured through surface coating.
Questions:
1. Explain the construction of the ‘Euro Tunnel’.

2. State the benefits of the construction of the ‘Euro Tunnel’.


1. Define “Glazing”, Explain different kind of glasses used for glazing purpose?

2. What is meant by mechanical handling? List the important safety guidelines for mechanical handling.

END OF SECTION C



No comments:

Post a Comment