assignmentssolution@gmail.com

Get Assignments and Projects prepared by experts at a very nominal fee.

More than 8 years in assisting assignments and projects/dissertation/thesis of MBA,BBA,BCA,MCA,PhD and others-

Contact us at : Email : assignmentssolution@gmail.com

Help for : SMU, IIBM,IMT, NMIMS, NIBM ,KSBM, KAIZAN, ISBM, SYMBIOSIS, NIMS, IGNOU, XAVIER, XIBMS, ISM, PSBM, NSBM, NIRM, ISBM, ISMRC, ICMIND, UPES and many others.

Help in : Assignments, projects, M.Phil,Ph.D disseration & thesis,case studies

Courses,MBA,BBA,PhD,MPhil,EMBA,MIB,DMS,MMS,BMS,GDS etc

Contact us at : Email : assignmentssolution@gmail.com



Thursday 22 October 2020

NMIMS December 2020: Contact us for answers at assignmentssolution@gmail.com

 

NMIMS Global Access
School for Continuing Education (NGA-SCE)
Course
: Project Management
Internal Assignment Applicable December 2020 Examination
Assignment Marks: 30


1. A software development project was planned to be completed in 12 months. The review
of the project after eight months revealed that Rs. 120000 was spent on the project for
48% of project completion. Consider total project budget as Rs 240000. Calculate and
explain the schedule and cost performance index for this situation. (10 Marks)

2. Take an example of developing a residential project and carry out the project feasibility
analysis using the six laws of project feasibility. (10 Marks)
3. You are given the task of preparing project plan for the “Annual Day Function” of your
college.
a. Explain work break-down structure and prepare three levels of work break-down
structure for this project plan. (5 Marks)
b. Consider hypothetical activities (4-5 tasks) and a project team of 3-4 positions. Prepare
RACI Model for the given project plan. (5 Marks)
**********

No comments:

Post a Comment