Internal Assignment Applicable December 2020 Examination
Assignment Marks: 30
1.
A software development project was planned to be completed in 12 months. The
review
of
the project after eight months revealed that Rs. 120000 was spent on the
project for
48%
of project completion. Consider total project budget as Rs 240000. Calculate
and
explain
the schedule and cost performance index for this situation. (10 Marks)
2. Take an example of developing a residential
project and carry out the project feasibility
analysis using the six laws of project feasibility. (10
Marks)
3. You are given the task of preparing project plan for the
“Annual Day Function” of your
college.
a. Explain work break-down structure and prepare three levels of
work break-down
structure for this project plan. (5 Marks)
b. Consider hypothetical activities (4-5 tasks) and a project
team of 3-4 positions. Prepare
RACI Model for the given project plan. (5 Marks)
**********