1 What are phases of project lifecycle?
List the advantages of project management.
A List the FIVE phases of project lifecycle and
briefly discuss each phase
List the TEN advantages of project
management
5
5
10
2
Write short notes on:
? Project organisation
? Term loans as a means of financing projects
A
Briefly explain
? Project organisation
? Term loans as a means of financing
projects
5
5
10
3 Explain the concept of Social Cost Benefit Analysis (SBCA)? List the application of
SBCA and describe the challenges in SBCA.
A Explain the importance of SBCA, discuss the
social impact of projects
List the TWO applications of SBCA
Discuss the FIVE challenges in SBCA
3
2
5
10
4 Discuss the financing of a power project.
A Elucidate which are key project parties in a
power project
Mention the key points of PPA(Power Purchase
Agreement)
Discuss the 3-tier security payment mechanism
2
5
3
10
5 Explain the types of procurement contracts.
A List the THREE types of procurement contracts
Discuss the THREE types of procurement
contracts
1
9
10
6 What is the purpose of project evaluation? Which the four dimensions of the project
explain the purpose of project evaluation?
A Mention the purpose of project evaluation
List the four dimensions of the project that
explain the purpose of project evaluation
Discuss four dimensions of the project that
explain the purpose of project evaluation
1
1
8 ( 2 marks for each
dimension)
10
*A-Answer
Note –Please provide keywords, short answer, specific terms, specific examples and marks
break - up (wherever necessary)
Note –Answer all questions. Kindly note that answers for 10 marks questions should be
approximately of 400 words. Each question is followed by evaluation scheme.
***********
ASSIGNMENT
DRIVE SUMMER 2015
PROGRAM MBADS (SEM 3/SEM 5)
MBAFLEX/ MBA (SEM 3)
PGDPMN (SEM 1)
SUBJECT CODE & NAME PM0011 – PROJECT PLANNING AND SCHEDULING
BK ID B1937
CREDIT AND MARKS 4 CREDITS AND 60 MARKS
Note –Answer all questions. Kindly note that answers for 10 marks questions should be
approximately of 400 words. Each question is followed by evaluation scheme.
Q.No Criteria Marks Total Marks
1 Write short note on:
? Project Rating Index(PRI)
? Scope change control
A Briefly explain:
? Project Rating Index(PRI)
? Partnering
10 (5 marks each)
10
2 Budget Estimation of ABC Company Ltd.
ABC Company Ltd., established in 1985, is engaged in the manufacturing of leather
accessories. Over the years, the company, which started out as a local firm,has made
its mark as an international corporation. However, the company is still working as a
traditional set up.
The high quality and durability of products have increased the demand of the products
in the market. As the production of the organisation is being increased to meet the
demand, the traditional set up is creating hurdles in the production process.
Organisation conflicts have arisen among the team members because of the
unorganised hierarchical structure of the company, which is affecting the output of the
organisation. Now that the management has decided to expand the business and
opened up branches abroad, the company is facing two more problems. The first
problem is in budgeting as the company is unfamiliar with international market
conditions, strategy, and business policy while the second problem is conflicts at the
time of team formation due to lack of experience of and exposure to multinational
work
culture, which has further affected the output of the company.
The company can estimate the budget through two methods, the bottom - up
approach and the top - down approach. The bottom -up approach is generally
followed by the MNCs as it is more accurate and reliable.
Mr.Parag has been appointed as the country head of the company and he has also
been assigned the responsibility of incorporating the advanced project set up in the
organisation.
Questions:
1. Which project estimation approach should be used by the company and why?
2. What type of project organisation structure should be used by the company
and why?
A 1. Argue the pros and cons of each
project estimation approach
Recommend the project estimation
approach that best suits the company
List the reasons for your decision by
mentioning the data from the case
2. Describe the existing organisation
structure
List the disadvantages of this structure
Recommend the project organisation
structure that should be used by the
company.
Give you reasons for recommending
this structure based on the data given
in the case and your knowledge on the
FIVE organizational structures.
2
1
2
1
1
1
2
10
10
3 What is the importance of operational feasibility? Explain the factors that affect
operational feasibility.
A Mention the importance of operational
feasibility
Discuss the FOUR factors that affect
operational feasibility
2
8
10
4 Write short notes on
? Monte Carlo analysis
? Work break down structure
A Briefly explain:
? Monte Carlo analysis
? Work break down structure
10 ( 5 marks each) 10
5 What do you understand by cost of quality? Elaborate on various types of costs of
quality associated with a project.
A Write the meaning of cost of quality
Briefly explain each types of costs of quality
associated with a project
1
9 (1. 5 marks for
each cost of quality)
10
6 Explain some of ISO standards that should be considered by the project manager
during project execution. List the advantages of project management software.
A Discuss the FOUR ISO standards that should
be considered by the project manager during
project execution
List any four advantages of project
management software
8 (2 marks each)
2(0.5 marks each)
10
*A-Answer
***********
ASSIGNMENT
DRIVE SUMMER 2015
PROGRAM MBADS (SEM 3/SEM 5)
MBAFLEX/ MBA (SEM 3)
PGDPMN (SEM 1)
SUBJECT CODE & NAME PM 0012 – PROJECT FINANCE AND BUDGETING
BK ID B1938
CREDIT AND MARKS 4 CREDITS AND 60 MARKS
Note –Answer all questions. Kindly note that answers for 10 marks questions should be
approximately of 400 words. Each question is followed by evaluation scheme.
Q.No Criteria Marks Total Marks
1 Write short notes on:
? Key project resources
? Three main requirements of funding a project through project finance
? Medium term financing for projects
? Bottom up estimation for creating project budget
A Briefly explain
? Key project resources
? Three main requirements of funding a
project through project finance
? Medium term financing for projects
? Bottom up estimation for creating
project budget
10 (2.5 marks each) 10
2
What is off take contract? Explain the various types of off take contracts.
A Describe the off take contract, where is it used,
how it helps the organisation, when is it
negotiated
Discuss the SIX types of off take contracts
4
6
10
3 Explain the different key project documents.
A
Description of key project documents.
10 (2 marks each) 10
4 Write short notes on:
? Project parties in a construction project
? Types of working capital
? Project cash flows
? Payback period method used to evaluate an investment on a project
A Briefly explain
? Project parties in a construction project
? Types of working capital
? Project cash flows
? Payback period method used to
evaluate an investment on a project
10 (2.5 marks each) 10
5
What are the problems associated with BOOT projects.
A Explanation of the main problems associated
with BOOT projects
Conclusion
9 (3 marks each)
1
10
6 Explain the different types of management contracts (a type of PPP ).
A List the types of management contracts
Explain each type of management contract
1
9(3 marks each)
10
*A-Answer
***********
ASSIGNMENT
DRIVE SUMMER 2015
PROGRAM MBADS (SEM 3/SEM 5)
MBAFLEX/ MBA (SEM 3)
PGDPMN (SEM 1)
SUBJECT CODE & NAME PM 0013 – MANAGING HUMAN RESOURCES IN
PROJECTS
BK ID B1939
CREDIT AND MARKS 4 CREDITS AND 60 MARKS
Note –Answer all questions. Kindly note that answers for 10 marks questions should be
approximately of 400 words. Each question is followed by evaluation scheme.
Q.No Criteria Marks Total Marks
1 Write short notes on:
? Characteristics of a project
? Objectives of human resource management
? Project team members
? Need for a project team
A Briefly explain
? Characteristics of a project
? Objectives of human resource
management
? Project team members
? Need for a project team
10 (2.5 marks each) 10
2 Explain the various conflict resolution techniques.
A Give a brief description various conflict
resolution techniques
10(1.25 marks each) 10
3
Write short notes on
? Skills required by a project manager
? Delphi technique of estimating manpower requirements of projects
? Importance of leadership in project management
? Goal setting theory
A
Briefly explain
? Skills required by a project manager
? Delphi technique of estimating
manpower requirements of projects
10 (2.5 marks each) 10
? Importance of leadership in project
management
? Goal setting theory
4 Explain the modern methods of performance management?
A List the six modern methods of performance
management
Explain the six modern methods of
performance management
1
9
( 1.5 mark for each
method)
10
5 Explain various types of collective bargaining.
A Explanation of four types of collective
bargaining
10 (2.5 marks each) 10
6 Discuss the concept of issue logs.
A Explain what is an issue log
Why should project managers solve issues,
give examples
What details does an issue log contain
Explain how this issue log helps a project
manager
1
2
5
2
10
*A-Answer
***********
DRIVE SUMMER 2015
PROGRAM MBADS (SEM 3/SEM 5)
MBAFLEX/ MBA (SEM 3)
PGDPMN (SEM 1)
SUBJECT CODE & NAME PM 0010 – INTRODUCTION TO PROJECT MANAGEMENT
BK ID B1936
CREDIT & MARKS 4 CREDITS & 60 MARKS
Note –Answer all questions. Kindly note that answers for 10 marks questions should be
approximately of 400 words. Each question is followed by evaluation scheme.
Q.No Criteria Marks Total Marks
1 What are phases of project lifecycle?
List the advantages of project management.
A List the FIVE phases of project lifecycle and
briefly discuss each phase
List the TEN advantages of project
management
5
5
10
2
Write short notes on:
? Project organisation
? Term loans as a means of financing projects
A
Briefly explain
? Project organisation
? Term loans as a means of financing
projects
5
5
10
3 Explain the concept of Social Cost Benefit Analysis (SBCA)? List the application of
SBCA and describe the challenges in SBCA.
A Explain the importance of SBCA, discuss the
social impact of projects
List the TWO applications of SBCA
Discuss the FIVE challenges in SBCA
3
2
5
10
4 Discuss the financing of a power project.
A Elucidate which are key project parties in a
power project
Mention the key points of PPA(Power Purchase
Agreement)
Discuss the 3-tier security payment mechanism
2
5
3
10
5 Explain the types of procurement contracts.
A List the THREE types of procurement contracts
Discuss the THREE types of procurement
contracts
1
9
10
6 What is the purpose of project evaluation? Which the four dimensions of the project
explain the purpose of project evaluation?
A Mention the purpose of project evaluation
List the four dimensions of the project that
explain the purpose of project evaluation
Discuss four dimensions of the project that
explain the purpose of project evaluation
1
1
8 ( 2 marks for each
dimension)
10
*A-Answer
Note –Please provide keywords, short answer, specific terms, specific examples and marks
break - up (wherever necessary)
Note –Answer all questions. Kindly note that answers for 10 marks questions should be
approximately of 400 words. Each question is followed by evaluation scheme.
***********
ASSIGNMENT
DRIVE SUMMER 2015
PROGRAM MBADS (SEM 3/SEM 5)
MBAFLEX/ MBA (SEM 3)
PGDPMN (SEM 1)
SUBJECT CODE & NAME PM0011 – PROJECT PLANNING AND SCHEDULING
BK ID B1937
CREDIT AND MARKS 4 CREDITS AND 60 MARKS
Note –Answer all questions. Kindly note that answers for 10 marks questions should be
approximately of 400 words. Each question is followed by evaluation scheme.
Q.No Criteria Marks Total Marks
1 Write short note on:
? Project Rating Index(PRI)
? Scope change control
A Briefly explain:
? Project Rating Index(PRI)
? Partnering
10 (5 marks each)
10
2 Budget Estimation of ABC Company Ltd.
ABC Company Ltd., established in 1985, is engaged in the manufacturing of leather
accessories. Over the years, the company, which started out as a local firm,has made
its mark as an international corporation. However, the company is still working as a
traditional set up.
The high quality and durability of products have increased the demand of the products
in the market. As the production of the organisation is being increased to meet the
demand, the traditional set up is creating hurdles in the production process.
Organisation conflicts have arisen among the team members because of the
unorganised hierarchical structure of the company, which is affecting the output of the
organisation. Now that the management has decided to expand the business and
opened up branches abroad, the company is facing two more problems. The first
problem is in budgeting as the company is unfamiliar with international market
conditions, strategy, and business policy while the second problem is conflicts at the
time of team formation due to lack of experience of and exposure to multinational
work
culture, which has further affected the output of the company.
The company can estimate the budget through two methods, the bottom - up
approach and the top - down approach. The bottom -up approach is generally
followed by the MNCs as it is more accurate and reliable.
Mr.Parag has been appointed as the country head of the company and he has also
been assigned the responsibility of incorporating the advanced project set up in the
organisation.
Questions:
1. Which project estimation approach should be used by the company and why?
2. What type of project organisation structure should be used by the company
and why?
A 1. Argue the pros and cons of each
project estimation approach
Recommend the project estimation
approach that best suits the company
List the reasons for your decision by
mentioning the data from the case
2. Describe the existing organisation
structure
List the disadvantages of this structure
Recommend the project organisation
structure that should be used by the
company.
Give you reasons for recommending
this structure based on the data given
in the case and your knowledge on the
FIVE organizational structures.
2
1
2
1
1
1
2
10
10
3 What is the importance of operational feasibility? Explain the factors that affect
operational feasibility.
A Mention the importance of operational
feasibility
Discuss the FOUR factors that affect
operational feasibility
2
8
10
4 Write short notes on
? Monte Carlo analysis
? Work break down structure
A Briefly explain:
? Monte Carlo analysis
? Work break down structure
10 ( 5 marks each) 10
5 What do you understand by cost of quality? Elaborate on various types of costs of
quality associated with a project.
A Write the meaning of cost of quality
Briefly explain each types of costs of quality
associated with a project
1
9 (1. 5 marks for
each cost of quality)
10
6 Explain some of ISO standards that should be considered by the project manager
during project execution. List the advantages of project management software.
A Discuss the FOUR ISO standards that should
be considered by the project manager during
project execution
List any four advantages of project
management software
8 (2 marks each)
2(0.5 marks each)
10
*A-Answer
***********
ASSIGNMENT
DRIVE SUMMER 2015
PROGRAM MBADS (SEM 3/SEM 5)
MBAFLEX/ MBA (SEM 3)
PGDPMN (SEM 1)
SUBJECT CODE & NAME PM 0012 – PROJECT FINANCE AND BUDGETING
BK ID B1938
CREDIT AND MARKS 4 CREDITS AND 60 MARKS
Note –Answer all questions. Kindly note that answers for 10 marks questions should be
approximately of 400 words. Each question is followed by evaluation scheme.
Q.No Criteria Marks Total Marks
1 Write short notes on:
? Key project resources
? Three main requirements of funding a project through project finance
? Medium term financing for projects
? Bottom up estimation for creating project budget
A Briefly explain
? Key project resources
? Three main requirements of funding a
project through project finance
? Medium term financing for projects
? Bottom up estimation for creating
project budget
10 (2.5 marks each) 10
2
What is off take contract? Explain the various types of off take contracts.
A Describe the off take contract, where is it used,
how it helps the organisation, when is it
negotiated
Discuss the SIX types of off take contracts
4
6
10
3 Explain the different key project documents.
A
Description of key project documents.
10 (2 marks each) 10
4 Write short notes on:
? Project parties in a construction project
? Types of working capital
? Project cash flows
? Payback period method used to evaluate an investment on a project
A Briefly explain
? Project parties in a construction project
? Types of working capital
? Project cash flows
? Payback period method used to
evaluate an investment on a project
10 (2.5 marks each) 10
5
What are the problems associated with BOOT projects.
A Explanation of the main problems associated
with BOOT projects
Conclusion
9 (3 marks each)
1
10
6 Explain the different types of management contracts (a type of PPP ).
A List the types of management contracts
Explain each type of management contract
1
9(3 marks each)
10
*A-Answer
***********
ASSIGNMENT
DRIVE SUMMER 2015
PROGRAM MBADS (SEM 3/SEM 5)
MBAFLEX/ MBA (SEM 3)
PGDPMN (SEM 1)
SUBJECT CODE & NAME PM 0013 – MANAGING HUMAN RESOURCES IN
PROJECTS
BK ID B1939
CREDIT AND MARKS 4 CREDITS AND 60 MARKS
Note –Answer all questions. Kindly note that answers for 10 marks questions should be
approximately of 400 words. Each question is followed by evaluation scheme.
Q.No Criteria Marks Total Marks
1 Write short notes on:
? Characteristics of a project
? Objectives of human resource management
? Project team members
? Need for a project team
A Briefly explain
? Characteristics of a project
? Objectives of human resource
management
? Project team members
? Need for a project team
10 (2.5 marks each) 10
2 Explain the various conflict resolution techniques.
A Give a brief description various conflict
resolution techniques
10(1.25 marks each) 10
3
Write short notes on
? Skills required by a project manager
? Delphi technique of estimating manpower requirements of projects
? Importance of leadership in project management
? Goal setting theory
A
Briefly explain
? Skills required by a project manager
? Delphi technique of estimating
manpower requirements of projects
10 (2.5 marks each) 10
? Importance of leadership in project
management
? Goal setting theory
4 Explain the modern methods of performance management?
A List the six modern methods of performance
management
Explain the six modern methods of
performance management
1
9
( 1.5 mark for each
method)
10
5 Explain various types of collective bargaining.
A Explanation of four types of collective
bargaining
10 (2.5 marks each) 10
6 Discuss the concept of issue logs.
A Explain what is an issue log
Why should project managers solve issues,
give examples
What details does an issue log contain
Explain how this issue log helps a project
manager